Launch Interactive Practice Room Excessive leakage and premature failure of valve packing is a result of __________.
A
opening a valve too quickly
B
jamming a valve in the closed position
C
low pressure fluid flow through the pipeline
D
a scored valve stem
✓ Correct Answer
USCG NMC Regulatory Explanation
In USCG Marine Engineering General Subjects, for engine room systems involving 'Excessive leakage and premature failure of valve packing is a result of', the standard operating requirement is: 'a scored valve stem'.