After packing is added to the stern tube stuffing box, which of the following procedures should be observed to insure even tightening of the gland?

A
Listen for a smooth, regular sound.
B
Measure the distance between the gland and the stuffing box with a rule. ✓ Correct Answer
C
Judge by feeling the gland for an increase in heat as it is being tightened up.
D
Open the drain connection to allow seawater to flow in and make the distance even.