BIGF Exit Exam • Set 6 Question 14 of 30

The duct should also be pressure tested to show that It ran withstand the ed ____ at gas pipe rup

✓

Direct Answer

Option B: lower pressure

The outer duct or double-wall casing of a gas fuel pipe must be pressure tested to prove it can safely withstand the maximum expected pressure in the event of high-pressure inner pipe rupture.

All Options

A
least pressure
B
lower pressure (Correct Answer)
C
maximum pressure
D
minimum pressure at gas pipe rup

Detailed Explanation & Context

The outer duct or double-wall casing of a gas fuel pipe must be pressure tested to prove it can safely withstand the maximum expected pressure in the event of high-pressure inner pipe rupture.

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • Basic Training for Ships subject to the IGF Code (BIGF).

Advertisement

Practice Full BIGF Set 6

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...