OCTCO/OCTF Exit Exam • Set 6 Question 16 of 30

When the IG plant is shutdown, the IBC cooling water should be let on the scrubber for at least ____hour(s)?

✓

Direct Answer

Option C: 3

When shutting down the inert gas plant, cooling water to the scrubber tower must be kept running for at least 3 hours (or per manufacturer instructions) to wash away acidic deposits and cool the internal packing.

All Options

A
1
B
2
C
3 (Correct Answer)
D
4

Detailed Explanation & Context

When shutting down the inert gas plant, cooling water to the scrubber tower must be kept running for at least 3 hours (or per manufacturer instructions) to wash away acidic deposits and cool the internal packing.

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • Oil and Chemical Tanker Cargo Operations (OCTCO/OCTF).

Advertisement

Practice Full OCTCO/OCTF Set 6

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...