OCTCO/OCTF Exit Exam • Set 6 Question 12 of 30
Which party is responsible for arranging the reducers or enlarger short pieces to the manifold?
✓
Direct Answer
Option A: The Cargo supplier
During tanker-terminal operations, the terminal/cargo supplier is responsible for providing and fitting the required manifold reducers or spool pieces to match the shore loading arms.
All Options
A
The Cargo supplier
(Correct Answer)
B
The Cargo Surveyors
C
The Ships Mooring crew
D
The tankers staff for the operation
Detailed Explanation & Context
During tanker-terminal operations, the terminal/cargo supplier is responsible for providing and fitting the required manifold reducers or spool pieces to match the shore loading arms.
Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • Oil and Chemical Tanker Cargo Operations (OCTCO/OCTF).