BIGF Exit Exam • Set 5 Question 11 of 30

To ensure no release occurs during the hook-up or disconnect of any components during the bunkering process

✓

Direct Answer

Option B: gassing up of the bunker piping systems with LNG prior to connect or disconnect 5 necessary

To prevent accidental atmospheric releases during bunkering connection or disconnection, bunker manifolds must be inerted and verified gas-free before breaking flanges.

All Options

A
draining of the bunker piping systems prior to connect or disconnect s necessary
B
gassing up of the bunker piping systems with LNG prior to connect or disconnect 5 necessary (Correct Answer)
C
purging of the bunker piping systems with inert gas prior to connect or disconne s recei
D
none of the above

Detailed Explanation & Context

To prevent accidental atmospheric releases during bunkering connection or disconnection, bunker manifolds must be inerted and verified gas-free before breaking flanges.

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • Basic Training for Ships subject to the IGF Code (BIGF).

Advertisement

Practice Full BIGF Set 5

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...