To ensure no release occurs during the hook-up or disconnect of any components during the bunkering process
Direct Answer
Option B: gassing up of the bunker piping systems with LNG prior to connect or disconnect 5 necessary
To prevent accidental atmospheric releases during bunkering connection or disconnection, bunker manifolds must be inerted and verified gas-free before breaking flanges.
All Options
Detailed Explanation & Context
To prevent accidental atmospheric releases during bunkering connection or disconnection, bunker manifolds must be inerted and verified gas-free before breaking flanges.
Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • Basic Training for Ships subject to the IGF Code (BIGF).
Practice Full BIGF Set 5
Test yourself with 30 interactive questions, live timer, and instant score.