GSK Exit Exam • Set 3 Question 2 of 30

Proof Load of derrick / crane is

✓

Direct Answer

Option A: More than safe working load

The Proof Load of a derrick or crane is defined as the load that the equipment can withstand without permanent deformation or failure. It is always specified as being more than the Safe Working Load (SWL) to ensure a margin of safety.

All Options

A
More than safe working load (Correct Answer)
B
Same as safe working Load
C
Less than
D
More than breaking strength

Detailed Explanation & Context

The Proof Load of a derrick or crane is defined as the load that the equipment can withstand without permanent deformation or failure. It is always specified as being more than the Safe Working Load (SWL) to ensure a margin of safety.

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • General Ship Knowledge (GSK).

Advertisement

Practice Full GSK Set 3

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...