HV Exit Exam • Set 1 Question 3 of 30

What safety document MUST be issued before performing maintenance on High Voltage switchgear?

Direct Answer

Option C: High Voltage Permit to Work (PTW) and Sanction to Test

HV PTWs enforce formal isolation, proving dead, earthing, key interlocking, and authorized signatures.

All Options

A
Verbal approval
B
Deck log entry
C
High Voltage Permit to Work (PTW) and Sanction to Test (Correct Answer)
D
Hot Work Permit only

Detailed Explanation & Context

HV PTWs enforce formal isolation, proving dead, earthing, key interlocking, and authorized signatures.

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • High Voltage Safety Officer & Switchgear Operations (HV).

Advertisement

Practice Full HV Set 1

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...