What maintenance step is required before cleaning HV switchboard busbar compartments?

✓

Direct Answer

Option A: Complete isolation, prove dead, apply portable earths, post warning signs, and issue HV PTW

High Voltage safety management requires a strict Permit to Work (PTW) system. Isolation, proving dead, and applying portable earths are mandatory to eliminate stored energy and induced voltages. These steps, aligned with industry best practices for HV safety, ensure a safe working environment before any physical contact with busbars.

All Options

A
Complete isolation, prove dead, apply portable earths, post warning signs, and issue HV PTW (Correct Answer)
B
Spray solvent live
C
Blow compressed air live
D
Wipe live with damp cloth

Detailed Explanation & Context

High Voltage safety management requires a strict Permit to Work (PTW) system. Isolation, proving dead, and applying portable earths are mandatory to eliminate stored energy and induced voltages. These steps, aligned with industry best practices for HV safety, ensure a safe working environment before any physical contact with busbars.

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • High Voltage Safety Officer & Switchgear Operations (HV).

Advertisement

Practice Full HV Set 2

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...