The number of power-frequency AC cycles in which a modern high-speed circuit breaker completes its tripping and arc clearing operation is:

Direct Answer

Option A: 2 to 5 cycles

Modern high-speed circuit breakers clear short-circuit faults within 2 to 5 cycles (30 to 100 ms on a 50/60 Hz system).

All Options

A
2 to 5 cycles (Correct Answer)
B
10 to 18 cycles
C
20 to 30 cycles
D
40 to 50 cycles

Detailed Explanation & Context

Modern high-speed circuit breakers clear short-circuit faults within 2 to 5 cycles (30 to 100 ms on a 50/60 Hz system).

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • High Voltage Safety Officer & Switchgear Operations (HV).

Advertisement

Practice Full HV Set 7

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...