Submerged cargo pumps cofferdam leakage is tested by the following intervals?

✓

Direct Answer

Option D: Every monthly & suitably after every operation of discharge/ballasting.

Submerged hydraulically driven cargo pump cofferdams must be purged and tested for seal leakage monthly and routinely after every cargo discharge or ballasting operation.

All Options

A
Every 6 months
B
Every 12 months
C
Every month
D
Every monthly & suitably after every operation of discharge/ballasting. (Correct Answer)

Detailed Explanation & Context

Submerged hydraulically driven cargo pump cofferdams must be purged and tested for seal leakage monthly and routinely after every cargo discharge or ballasting operation.

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • Oil and Chemical Tanker Cargo Operations (OCTCO/OCTF).

Advertisement

Practice Full OCTCO/OCTF Set 8

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...