Under SOLAS, what is the minimum required capacity of inert gas plant relative to maximum cargo discharge rate?
Direct Answer
Option D: At least 125% of the maximum required cargo discharge pumping rate
SOLAS Chapter II-2 requires inert gas plant capacity to be at least 125% of the maximum rated cargo discharge capacity to maintain positive pressure across all tanks during maximum outloading.
All Options
Detailed Explanation & Context
SOLAS Chapter II-2 requires inert gas plant capacity to be at least 125% of the maximum rated cargo discharge capacity to maintain positive pressure across all tanks during maximum outloading.
Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • Advanced Training for Oil Tanker Cargo Operations (TASCO).