USCG USCG Safety Eng
Set 4 • Question #105 of 254
Launch Interactive Practice Room What must be accurately determined to assess the potential for progressive flooding after a MODU has been damaged?
A
The integrity of the watertight boundaries.
✓ Correct Answer
B
The capacity of the water sprinkler system.
C
The operation of the machinery space bilge level alarms.
D
All of the above.
USCG NMC Regulatory Explanation
Under MARPOL, SOLAS, and USCG Marine Engineering Safety regulations, regarding 'What must be accurately determined to assess the potential for progressive flooding after a MODU has been damaged', the mandated standard is: 'The integrity of the watertight boundaries.'.
Question Discussion & Notes
0Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.
Loading mariner discussions...