Launch Interactive Practice Room When personnel are lifted by a helicopter from an inflatable liferaft, the personnel on the raft should __________.
A
deflate the floor of the raft to reduce the danger of capsizing
✓ Correct Answer
B
inflate the floor of the raft to provide for additional stability
C
remove their lifejackets to prepare for the transfer
D
take in the sea anchor to prevent fouling of the rescue sling
USCG NMC Regulatory Explanation
Under MARPOL, SOLAS, and USCG Marine Engineering Safety regulations, regarding 'When personnel are lifted by a helicopter from an inflatable liferaft, the personnel on the raft should', the mandated standard is: 'deflate the floor of the raft to reduce the danger of capsizing'.