Launch Interactive Practice Room The maximum draft to which a mobile offshore drilling unit may be safely loaded is called __________.
A
mean draft
B
calculated draft
C
deep draft
D
load line draft
✓ Correct Answer
USCG NMC Regulatory Explanation
Under MARPOL, SOLAS, and USCG Marine Engineering Safety regulations, regarding 'The maximum draft to which a mobile offshore drilling unit may be safely loaded is called', the mandated standard is: 'load line draft'.