OCTCO/OCTF Exit Exam • Set 9 Question 2 of 30

What are consequences of a ballast tank vent not working during deballasting operation?

✓

Direct Answer

Option A: The tank de pressurization and denting of side plates.

If a ballast tank air vent / vacuum valve fails during high-rate deballasting, internal vacuum can cause tank depressurization and severe structural buckling or denting of side shell plates.

All Options

A
The tank de pressurization and denting of side plates. (Correct Answer)
B
The tanks taking in cargo vapors during loading operation.
C
The cargo tank alteration of ullage are taking place.
D
Combination of all three a,b,c

Detailed Explanation & Context

If a ballast tank air vent / vacuum valve fails during high-rate deballasting, internal vacuum can cause tank depressurization and severe structural buckling or denting of side shell plates.

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • Oil and Chemical Tanker Cargo Operations (OCTCO/OCTF).

Advertisement

Practice Full OCTCO/OCTF Set 9

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...